Project Details
| DISTRICT AND EA | 01-0H4104 |
| County - Route - Postmile | HUM-169-15/33.8 |
| Location | Humboldt County Near Weitchpec At Various Locations From 0.6 Mile East Of Pecwan Creek Bridge To Route 96 |
| Description of Work | Csp, Structural Concrete, And Rsp. |
| Contractor Name | R. BROWN CONSTRUCTION COMPANY,INC. |
| Bid Amount | $3,281,191.60 |
| Begin Construction Date | 2025/06/10 |
| Estimate Completion Date | 2026/12/15 |
| Percent Work Completed | 84% |
| District Phone Number | (707) 445-6600 |
| Storm Water Plan | WPCP |