Project Details
| DISTRICT AND EA | 03-3G6104 |
| County - Route - Postmile | YOL-5-14/22.8 |
| Location | Yolo County At And Near Zamora From 0.1 Mile South Of Adams Creek Bridge To 0.2 Mile North Of Route 505/5 Separation |
| Description of Work | Replace Rhma-O With Digouts. |
| Contractor Name | ALL-AMERICAN CONSTRUCTION, INC. |
| Bid Amount | $5,269,771.00 |
| Begin Construction Date | 2026/07/27 |
| Estimate Completion Date | 2026/10/19 |
| Percent Work Completed | 93% |
| District Phone Number | (530) 741-4572 |
| Storm Water Plan | WPCP |