Project Details
| DISTRICT AND EA | 04-1X1004 |
| County - Route - Postmile | SCL-9-4/4 |
| Location | On Rte 9 In Santa Clara Co Remove Debris, Clean Drainage System, And Regrade Slope Dir'S Order Emergency F.A. |
| Description of Work | Stabilize Slope And Remove Debris |
| Contractor Name | QA CONSTRUCTORS, INC |
| Bid Amount | Emergency project |
| Begin Construction Date | 2024/02/21 |
| Estimate Completion Date | 2026/05/03 |
| Percent Work Completed | 92% |
| District Phone Number | (510) 286-4444 |
| Storm Water Plan | NONE |