Project Details
| DISTRICT AND EA | 04-264724 |
| County - Route - Postmile | MRN-101-20.8/27.1 |
| Location | In Marin County In And Near Novato From 0.1 Mile South Of Franklin Avenue Overhead To 0.5 Mile South Of San Antonio Creek Bridge |
| Description of Work | Roadway And Bridge Widening For Hov |
| Contractor Name | GHILOTTI CONSTRUCTION COMPANY,INC. |
| Bid Amount | $78,860,144.47 |
| Begin Construction Date | 2022/07/07 |
| Estimate Completion Date | 2026/11/17 |
| Percent Work Completed | 99% |
| District Phone Number | (510) 286-4444 |