Project Details
| DISTRICT AND EA | 05-1H4704 |
| County - Route - Postmile | SCR-9-13.6/0 |
| Location | Santa Cruz County Near Boulder Creek At San Lorenzo River Bridge And At Kings Creek Bridge |
| Description of Work | Replace Bridges And Install Mgs. |
| Contractor Name | GORDON N. BALL, INC. |
| Bid Amount | $14,208,691.00 |
| Begin Construction Date | 2025/11/10 |
| Estimate Completion Date | 2028/09/01 |
| Percent Work Completed | 51% |
| District Phone Number | (805) 549-3111 |
| Storm Water Plan | WPCP |