| DISTRICT AND EA | 10-1F1804 |
| County - Route - Postmile | SJ-4-16/19.4 |
| Location | San Joaquin County In Stockton At Various Locations From 0.3 Mile East Of Route 4/5 Separation To 0.4 Mile West Of Route 4/99 Separation |
| Description of Work | Bridge Work, Concrete Barrier, And Install |
| Contractor Name | VIKING CONSTRUCTION COMPANY, INC. |
| Bid Amount | $26,248,389.25 |
| Begin Construction Date | 2024/02/29 |
| Estimate Completion Date | 2026/08/21 |
| Percent Work Completed | 100% |
| District Phone Number | (209) 948-7543 |
| Storm Water Plan | SWPPP |