Project Details
| DISTRICT AND EA | 11-2N2374 |
| County - Route - Postmile | SD-5-40.6/72 |
| Location | San Diego County At Various Locations Fromsanta Fe Drive Undercrossing To San Mateo Creek Bridge |
| Description of Work | Grind Bridge, Overlay With Polyester Concr |
| Contractor Name | PETERSON-CHASE GENERAL ENGINEERING CONSTRUCTION, INC. |
| Bid Amount | $4,312,028.70 |
| Begin Construction Date | 2026/09/14 |
| Estimate Completion Date | 2027/02/16 |
| Percent Work Completed | 2% |
| District Phone Number | (619) 688-6699 |
| Storm Water Plan | WPCP |